Reference
Sampling and approval, stage by stage
16 to 20 days from an agreed brief, photographs approved before the sample ships, and why the sealed sample is the contract.
Specs and sizesOrdering · Lead times
Two published windows, and a sampling stage that sits in front of both. The common planning error is to treat the production window as the lead time; it is the last two thirds of it.
Beaded décor runs 40 to 60 days after sample approval. Bohemian and macramé work runs 60 to 90 days after sample approval. Sampling sits in front of both at usually 16 to 20 days from an agreed brief, and is quoted separately. Freight, inspection scheduling and any market testing sit outside the production window and are quoted per programme.
Forty to sixty days after sample approval for beaded décor. Sixty to ninety for bohemian and macramé. Those are the two windows Gemixx publishes, and no third window exists.
The important word is "after". The window begins at sample approval, not at purchase order and certainly not at first enquiry. Sampling sits in front of it at usually 16 to 20 days from an agreed brief, and the brief-agreement stage sits in front of that. A buyer planning to a 60-day lead time from the day they first write is planning to a number that does not describe anything.
Inside the production window the work runs in a fixed order. Beads are allocated against the colour-count sheet derived from the approved sample. Dyeing or melting happens where a colour is made to order. Strands are strung by hand to the sheet, with the strand length and bead sequence identical across the run because the sheet says so. Strands are fixed to the dowel, header rail or rod pocket in a set order so the panel hangs without drift. Hems are shaped where the design is shaped.
Then the run moves to the quality and packing house in Greater Noida for first-article and lot AQL inspection, assembly and kitting, and export packing and labelling.
Where the piece sits inside the window depends on three things: bead count, whether a colour has to be made to order, and whether the pattern is rule-strung or mapped.
A spaced, library-bead panel in a stock colour lands near the bottom of the window. A dense, mapped panel in a dyed-to-order colour lands near the top. Both are fair reads of the same published figure, which is why the figure is a range rather than a date.
Ask for a date rather than a duration, against your purchase order and your inspection arrangement. A duration is a category statistic; a date commits to your run. And ask what the date assumes about inspection scheduling and freight booking, because those two are outside the published window and are where otherwise-sound plans lose a fortnight.
An approved sample, and a purchase order against it. Also the packing and label artwork, which is needed by the export packing stage and is routinely supplied late. Artwork arriving after production finishes holds the run in the packing house for no good reason.
Where testing is required, the test commissioning decision has to be made at approval, not at shipment.
Reply within one business day. Formal quote within 48 hours of a complete specification. Sampling usually 16 to 20 days from an agreed brief. Production 40 to 60 days after approval, or 60 to 90 for bohemian and macramé.
Everything else — photograph approval, sample transit, your internal review, inspection scheduling, test turnaround, export packing, consolidation and ocean transit — is timed per programme and must be counted separately. The seasonal calendar does that counting backwards from a floor-set date.
Sampling is quoted separately from production. Testing is quoted per market. Inspection and freight are quoted per programme. Compression is agreed per programme rather than bought as an expedite service, on the basis of what can actually be run in parallel.
In the gap between sample approval and purchase order. The published window starts at approval, but nothing is actually allocated until there is an order, and a three-week internal approval cycle after a sample is approved silently moves the ship date by three weeks.
The second place is freight booking at season peaks. Production can finish on time and the load can still sit waiting for space. That is why the seasonal calendar counts freight as its own phase rather than folding it into production.
Most of the window is labour and almost none of it is machine time. That has two consequences for planning. First, the window is relatively insensitive to order size within normal ranges, because more pieces means more hands rather than longer machine runs. Second, it is very sensitive to design: a mapped pattern genuinely takes longer per piece than a rule-strung one, and no amount of scheduling changes that.
It also means a late specification change is more expensive than in a printed category. There is no plate to remake; there is a colour-count sheet to rewrite and a bead allocation to redo.
That the published window holds, and that the dates which slip are the ones outside it. In our own programme record the items which moved were sample approvals waiting on buyer-side review, colour amendments that triggered a fresh approval, and one wall-hanging construction that was re-engineered between the dowel version and the rod-pocket version — a construction change, and therefore a new approval rather than a delay inside an existing one.
One programme in the record carried a quoted 90-day lead time. Where a construction or a programme genuinely needs a longer window than the published one, it is quoted and written down at the start rather than discovered later.
Three neighbours carry the surrounding phases. Sampling is the window in front of production. The seasonal calendar is the backwards count through everything outside it. And freight and transit is the leg timed from your own freight data. Inside the window, the colour-count sheet is what makes the run repeatable, and macramé knotting is the construction that runs on the longer schedule.
The ship date or the ex-works date, not the duration. The window the date was derived from. The inspection arrangement and who attends. Whether the sealed sample travels to inspection. The latest acceptable arrival date, separately from the ship date, so freight has a target. And the consequence of a specification change, so both sides already know that a change resets the approval.
At approval: the approval itself and the purchase order. During production: nothing, by design — a programme being asked for weekly status is usually a programme whose dates were never agreed properly. At the end of production: the inspection report, then the packing list and shipping documents, then test reports where the market requires them.
Extractable data
| Phase | Duration | Status |
|---|---|---|
| Brief to agreed brief | Buyer-side; reply within one business day | Not a published window |
| Formal quote | Within 48 hours of a complete specification | Published |
| Sampling | Usually 16–20 days from an agreed brief | Published; quoted separately |
| Photograph approval and sample transit | Buyer-side plus freight | Not a published window |
| Production — beaded décor | 40–60 days after sample approval | Published |
| Production — bohemian and macramé | 60–90 days after sample approval | Published |
| Inspection | Scheduled against the run | Quoted per programme |
| Market testing | Commissioned against the approved sample | Quoted per market |
| Export packing, consolidation and freight | Per route and Incoterm | Quoted per programme |
Good to know
Production is 40 to 60 days after sample approval for beaded décor and 60 to 90 days for bohemian and macramé work. Those are the only two lead-time windows Gemixx publishes, and they begin at sample approval rather than at purchase order.
An approved sample. Nothing in the production window can begin against a brief, because the colour-count sheet, the bead allocation and the quality reference are all derived from the approved sample.
Production is quoted with the order. Sampling is quoted separately and sits before the window. Inspection, testing and freight are quoted per programme and sit outside it, which is the detail most often missed in planning.
Yes. Bohemian and macramé work runs 60 to 90 days after sample approval rather than 40 to 60. If a programme mixes beadwork and knotted work in one shipment, plan against the longer window.
Production can be partly compressed by running strand sets in parallel across the beadwork studios, agreed per programme rather than promised. What cannot be compressed is a dye lot, glass colour development with annealing trials, or the hand-stringing rate on a mapped pattern.
Inspection scheduling, testing duration, freight transit and any expedite arrangement. None of those has a published figure, and quoting one here would be an invention rather than a service.
A change touching bead, pattern or size is a new approval, and the window restarts from the new approval rather than continuing from the old one. A packing or labelling change usually does not move the date.
Keep exploring
Reference
16 to 20 days from an agreed brief, photographs approved before the sample ships, and why the sealed sample is the contract.
Specs and sizesReference
Counting backwards from a floor-set date through sampling, production, inspection, freight and receiving.
Compare the optionsPillar
Brief, rough cost sheet, colour match, sample, production, packing — the six stages with the real published timings.
Compare the optionsReference
The beadwork defect taxonomy, how each defect is detected, and which are rejects rather than repairs.
How it is madeReference
Every packing and labelling field a bead order needs, who supplies each value, and the two packing problems unique to beadwork.
Specs and sizes
Start a conversation
Send a reference, a colour chip or a sketch. Minimums are set per design and confirmed per quote; sampling is quoted separately and usually runs 16 to 20 days from an agreed brief.