Pillar
Applications by setting
Twenty settings, from a closet front to a hotel lobby, each with the format that suits it, the fixing it needs and the standard that applies.
Read the guide
Specification pillar
Written by the beadwork desk of a leading beaded-décor manufacturer, for the person who has to draw it, schedule it, coordinate it and then sign it off — not for the person buying a curtain.
Close hand-strung strands of honey and amber glass beads filling one side of the frame, the beads packed bead against bead down every cord.
A beadwork specification has to carry ten fields: product type, finished size, strand count or pitch, bead specification including the drill hole, colour references, pattern artwork, top fixing, edge shape and end beads, packing, and quantity with its destination. Beyond those, a drawing has to state tolerance and name the fire standard the project requires, because on a strung panel a classification belongs to the tested build.
With measuring an opening. Three measurements and a floor-gap decision, and most of the dimensional errors we see never happen.
Then density and view through, which is the one page that changes the answer to every other question. A denser panel is heavier, costs more, conceals more and transmits less light, and all four of those move together. A specifier who has settled density has settled most of the brief.
Nineteen pages, each owning one decision a specifier has to make before beadwork can be drawn, scheduled or signed off. They cover measurement, the performance questions that get asked in design reviews, the geometry a drawing has to carry, fixing into a real building, programme and budget, and what gets handed over at the end.

The spec table above is the field list underneath all of it. Ten fields: with all ten a panel can be quoted and sampled, and with nine somebody in the studio is deciding on your behalf.
By the order the decisions actually get made on a project. Measure the opening first, because nothing can be costed without dimensions. Then set density, because density drives weight, cost, privacy and light at once. Then the geometry — hem, colour under the real light source, tolerance. Then the building: substrate, ceiling fixing, sequencing. Then programme and budget. Then approval, maintenance and handover.
That sequence is deliberate. Most beadwork problems on site are caused by a decision made in the wrong order, usually a fixing chosen before a weight was known.
The performance set and the fixing set. Daylight and glare, privacy and sightlines, acoustic performance and airflow are the four questions that come up in a design review, and all four have real limits rather than performance figures.
Fixing into substrates, ceiling tracks and suspended fixings, and installation sequencing are the three the contractor will ask about. Tolerances in hand work is the one that prevents an argument at inspection, and fire performance in a specification is the one that has to be written carefully, because on a strung panel the classification belongs to the tested build rather than to the material.
Panel weight and fixing load are established on the build you specify. The approved sample is weighed, the fixing is sized to that weight, and the figure goes onto the tech pack as a recorded value — which is the only route to a number that is true for a specific build rather than for a category.
Fire performance works the same way. Specimens are built to the specified cord and header, and an accredited laboratory tests that build against the standard the project names.
Budget per opening, programme and lead-time planning, and what to sample before sign-off. Those three cover the three questions that arrive before anybody has drawn anything: what will it cost, when can I have it, and what do I need to see first.
Budget per opening is the most used of the three, because the opening — not the metre and not the square metre — is the unit beadwork is costed in.
The budget per opening, the programme dates, the test package and the spares allowance. All four depend on the opening count and the build, so all four are quoted rather than published.
What a specifier can take from these pages before a quote exists is the shape of the answer: which lever moves a budget, which phase moves a date, and which decisions have to be made before sampling rather than after.
The construction, the formats, the lead times and the inspection practice all come off beadwork we manufacture ourselves. Beaded décor runs 40 to 60 days after sample approval, sampling takes 16 to 20 days from an agreed brief, a door panel is about 90 by 200 cm, and thirty hand-strung strands on a single wooden dowel is the common build at that size.
The performance pages are written from how the materials behave in a hanging panel: how glass loads a cord, how wood moves with humidity, how a bone bead takes a drill, how a plated finish reads under warm light. Those are the things a plant learns by drawing, turning and stringing its own beads, and they are what a drawing needs before a sample exists.
Specification pages
Specification
Width at three heights, the drop against the floor gap, and the header depth — the measurements a quote needs.
Specification
Pitch against bead diameter, the open area it leaves, and how density moves weight and opacity together.
Specification
How pitch, diameter and opacity combine into a sightline — and the distance at which concealment stops working.
Specification
How transmission, refraction and cast bead-shadows behave through the day — and where glare control fails.
Specification
A hanging bead panel scatters a little high frequency and reduces nothing meaningfully — and what to specify instead.
Specification
Air passes, insects are discouraged rather than excluded, and pitch is the only lever that changes either.
Specification
Straight, scalloped, V-point, inverted-V, swag, diagonal and staggered — each with its longest and shortest drop.
Specification
Metamerism between daylight, tungsten and LED, and how to sign bead colour off under the real light source.
Specification
What hand-strung beadwork can hold on length, pitch, colour and count — and why a drawing has to say.
Specification
What to ask of the cord and the textile header, which standard to name, and what cannot be certified yet.
Specification
Plasterboard with and without a stud, timber, concrete and steel — and why the load has to be known first.
Specification
Tracks, joists, suspended rails and the services coordination a drawing has to show.
Specification
After painting and lighting, before furniture — with the header loaded dry first and settling time allowed.
Specification
Sampling, 40 to 60 days of production, freight, and where a specifier should hold float.
Specification
Why the opening is the budget unit, which five levers move the figure, and how to trade look against price early.
Specification
The colourway, one full strand, the header detail and the hem at full drop — the four things to see first.
Specification
A cleaning interval by setting, the method per material, who can reach the panel, and the spares held on site.
Specification
Spare beads by colour, pre-made replacement strands, the cord spec, and who re-strings a strand on site.
Specification
The colour-count sheet, bead references, fixing details, the care card and the spares inventory.
Extractable data
| Field | Unit | What hand work holds |
|---|---|---|
| Product type | Named format | Exact — it is a category, not a dimension |
| Finished size | mm or in: width × longest drop | Width closely; drop to a stated tolerance |
| Strand count or pitch | Count, or pitch in mm against a stated width | Per-strand pitch closely; cumulative width needs its own limit |
| Beads | Outside diameter and drill hole in mm, per bead | Pressed and moulded closely; hand-formed beads vary by nature |
| Colours | A colour reference or a physical chip per bead colour | Matched at approval; dye lots move between runs |
| Pattern | Artwork or a numbered reference image | Exact once mapped to a colour-count sheet |
| Top fixing | Header type and finished length in mm | Closely — it is a joinery component |
| Edge and ends | Hem profile, longest and shortest drop, end-bead reference | To a stated tolerance; shaped hems need the tightest |
| Packing | Master carton dimensions and pieces per master | To the carton specification |
| Quantity and destination | Units per colourway, named port or warehouse | Exact |
Good to know
Measuring an opening, then density and view through. The first gives you the dimensions a quote needs; the second gives you the one performance decision that changes everything else — weight, cost, privacy and how much light gets through.
The floor that makes the work. Construction, formats, tolerances and lead times are what our own plants hold to, and the performance pages are written from how glass, wood, bone and metal behave in a hanging panel. Where a value belongs to one build — panel weight, a fire classification — it is established on the approved sample and recorded on the tech pack.
The beadwork desk that will build it. Questions on anything missing come back within one business day, and a formal quote follows within 48 hours of a complete specification. The ten fields in the table above are the list a drawing is read against, and the drill hole is the one most often left off.
By the order the decisions get made: measure, then set density and performance, then draw the geometry, then fix it to the building, then programme it, then hand it over. Nineteen pages, each owning one decision.
The four a specifier asks for most, and each belongs to a build rather than to a catalogue. Fire classification is tested on the specified construction — bead, cord, header and mount together. Panel weight is taken off the approved sample and the fixing sized to it. Minimums are set per design and confirmed with your quote. And beadwork is a visual and spatial device rather than an acoustic one.
Keep exploring
Pillar
Twenty settings, from a closet front to a hotel lobby, each with the format that suits it, the fixing it needs and the standard that applies.
Read the guideReference
Specification sheets and definitions — the pages to send a designer before they draw.
See the detailReference
Five craft families — strung, embroidered, wire-wrapped, knotted and wrapped fibre — and what each one is good for.
Read the guideHub
The full beaded range — curtains, portals, valances, tabletop, cushions, textiles and beads — from a leading manufacturer that makes the bead as well as the piece.
Compare the optionsManufacturing
Strands that frame an opening and leave a clear walk-through: arched and inverted-V drops, built to order on a turned dowel or a stained rail.
See the detail
Start a conversation
Send a reference, a colour chip or a sketch. Minimums are set per design and confirmed per quote; sampling is quoted separately and usually runs 16 to 20 days from an agreed brief.