Ordering · Calendar

The seasonal calendar, counted backwards

Every seasonal failure in this category is the same arithmetic error: planning from the production window alone. This page counts backwards from the floor-set date through every phase, including the ones set per programme.

The short answer

Count backwards from the floor-set date through five phases: receiving and ticketing, ocean freight, inspection and export packing, production at 40 to 60 days after sample approval, and sampling at 16 to 20 days from an agreed brief. Only the last two have published durations; the other three are quoted per programme and must be counted with your own figures.

Key takeaways

  • Two phases have published durations. Three do not, and have to be counted with your own numbers.
  • Production is 40 to 60 days AFTER sample approval — approval is a date, not a formality.
  • A new design needs the sampling window in front of production. A repeat does not.
  • Build the approval gap in: sample transit plus internal review is routinely three weeks.
  • Knotted and bohemian work needs 60 to 90 days, so a mixed shipment plans to the longer window.

When must approval happen before a floor set?

Place the order so that sample approval happens at least 40 to 60 days before the goods have to leave India, and then add freight, inspection and your own receiving time on top. For a new design, add the sampling window and your internal approval cycle in front of that.

Only two of the phases in that sentence have published durations. Sampling is usually 16 to 20 days from an agreed brief; production is 40 to 60 days after sample approval for beadwork and 60 to 90 for bohemian and macramé. Freight, inspection scheduling and receiving do not have published figures and are not invented here — you fill them in from your own data.

How do you count back from a floor set?

Start at the floor-set date and walk backwards. Subtract your receiving, ticketing and distribution time. Subtract ocean transit and inland delivery for the route and Incoterm you are buying on. Subtract inspection, export packing and consolidation. Subtract the production window. You now have the required sample-approval date.

For a repeat of an already-approved style, that is the whole count, and it is comfortable. For a new design, keep going: subtract your internal approval cycle and the sample's own transit, then subtract the sampling window, then subtract the time it takes to agree the brief. That last number is the one buyers forget and the one most within their control.

Does a repeat order save the front end?

Whether the style is new. A repeat order against a sealed sample removes the entire front half of the count, because there is no brief to agree, no colour to match and no approval to wait for. A new style carries all of it.

Second, whether a colour or a bead has to be made to order. A dye lot or a glass melt sits in front of stringing, and glass colour development can require annealing trials before anyone strings a strand. That is a materials lead time, not a production one, and it is invisible in the published window.

Should you ask for a sample-approval date?

Ask for the required sample-approval date rather than the required order date. That reframes the conversation onto the only milestone that actually controls the production window, and it exposes immediately whether your own internal review cycle fits.

Then ask whether a repeat of an existing approved style could carry the season while a new style is developed for the one after it. In a tight calendar that is almost always the better answer.

Which two dates do we need?

Two dates, not one: the floor-set date and the latest acceptable arrival date at your warehouse. They imply different order dates and most briefs give only one. Supply both and the count can be done once rather than renegotiated.

After that, the colour references, because colour is the most common cause of a second sampling cycle and a second cycle is what breaks a seasonal plan.

How long does each seasonal stage take?

Brief agreement is buyer-paced, with a reply inside one business day from us. Quotation is 48 hours from a complete specification. Sampling is 16 to 20 days. Photograph approval is same-week if the reviewers are lined up. Sample transit is freight. Internal approval is routinely two to three weeks and is almost never budgeted. Production is 40 to 60 days, or 60 to 90 for knotted work. Inspection, export packing and consolidation are scheduled against the run. Freight is per route.

Order minimums should be confirmed in the same conversation, because a quantity agreed late can reset the schedule.

Which seasonal items are quoted separately?

Sampling, separately. Testing, per market, and commissioned against the approved sample. Inspection and freight, per programme. Compression is agreed per programme rather than bought as a rush service — it is a conversation about what can be parallelised, not a line item.

A seasonal programme does carry one real cost that an evergreen one does not: the cost of being wrong. A missed floor set is usually a markdown rather than a late delivery, which is why the conservative count is the cheap one.

Four neighbours supply the inputs to a backwards count. Sampling and lead times give the two published windows. Freight and transit gives the leg timed from your own freight data, driven by freight cubing. And where a market needs lab testing, that sits on the critical path too, commissioned against the approved sample rather than against the brief.

Where does a seasonal programme slip?

Three places, every time.

The approval gap. A sample is approved by development, then waits for a buying review, and the window silently starts three weeks late.

A colour amendment after approval. This is a new approval, and on a seasonal style it usually ends the season rather than delaying it.

Freight at peak. Production can finish on schedule and the load can still wait for space. Count freight as its own phase with its own risk, not as a tail on production.

A repeat against an approved tech pack removes the whole front half of the count, which is the only reliable way to hit a tight season.

Why is beadwork slow at the front?

It is slower at the front and more predictable at the back. The sampling and approval stage is heavier than in a printed category, because a strung panel cannot be fully judged from a drawing. Once a sample is sealed, though, the production window is stable, because the colour-count sheet makes every piece in the run identical by construction rather than by inspection.

The practical consequence is that beadwork rewards early decisions disproportionately. A programme that settles design and colour two months earlier does not finish two months earlier — it finishes with a season's margin instead of none.

Which seasonal dates actually work?

That the dates which work are the ones set backwards from a floor set, and that live programmes in our record have carried ship dates agreed months in advance, across multiple styles and destinations, with production scheduled into the following calendar year.

It also shows what happens to a design that arrives late in a buying cycle: it gets costed and re-costed while the window closes around it. Cost engineering works on a drawing, so it has to happen early. Time and cost are the same conversation in a seasonal programme.

Freight and transit is the phase timed from your own freight data, and inspection sits immediately before it.

Which dates belong on a seasonal order?

The ship date and the latest acceptable arrival date, separately. The required sample-approval date for a new style. The inspection window and who attends. The Incoterm, because it determines who is managing the freight phase of your own backwards count. And a stated consequence for a specification change, so both sides already know that a change resets the approval and therefore the season.

Extractable data

The backwards count, phase by phase

Durations marked published are Gemixx figures. Durations marked buyer-side or quoted are set by your own freight and receiving arrangements, so fill them in from your own data.
Phase, counting backwards from the floor setDurationSource
Receiving, ticketing and distribution to storeBuyer-sideYour own warehouse figures
Ocean freight and inland deliveryQuoted per route and IncotermQuoted per programme
Inspection, export packing and consolidationQuoted per programmeQuoted per programme
Production — beaded décor40–60 days after sample approvalPublished
Production — bohemian and macramé60–90 days after sample approvalPublished
Sample transit and internal approvalBuyer-sideYour own review cycle
SamplingUsually 16–20 days from an agreed briefPublished
Brief agreement and quotationReply in one business day; quote within 48 hours of a complete specificationPublished
Testing, where a market requires itQuoted per market, against the approved sampleQuoted per market

Good to know

Questions buyers ask about Seasonal order planning for beaded décor

Does it differ for macramé?

Yes, by a month at the production stage: 60 to 90 days after sample approval rather than 40 to 60. A shipment combining beadwork and knotted work has to be planned to the longer window, or split into two shipments with two dates.

What can be compressed, and what cannot?

The brief, the quote turnaround and the number of sampling rounds all compress. Production compresses only by agreement, by running strand sets in parallel. Freight at a seasonal peak does not compress at all, and neither does a dye lot.

What is confirmed per quote rather than published?

Freight transit, inspection scheduling, testing turnaround and any expedite arrangement. Three of the five phases in a backwards count therefore have to be filled in from your own data or from a quote, not from this page.

What happens if the specification changes mid-run?

The clock restarts from the new approval. On a seasonal programme that usually means the season is lost rather than delayed, which is the practical reason to resolve colour and construction before the sample rather than after it.

How long does this stage take?

For a new design, allow the sampling window plus your own approval cycle plus the production window plus freight. For a repeat of an approved style, only production and freight remain, which is why repeats are the only reliable way to hit a tight season.

What do you need from us first?

The floor-set date and the latest acceptable arrival date, as two separate dates. Most briefs give one date and leave us to guess which it is, and the two imply very different order dates.

Is this quoted separately?

Sampling is quoted separately from production, and testing is quoted per market. Both are decisions that have to be taken early in a seasonal count, because both sit on the critical path.

Keep exploring

Related pages

Index

Craft categories

Seventeen beaded objects documented from inside the craft — what each one is, how the tradition builds it, and what it would take to develop one.

How it is made

Pillar

How an order runs

Brief, rough cost sheet, colour match, sample, production, packing — the six stages with the real published timings.