Reference
Lead times after sample approval
40 to 60 days after sample approval for beadwork, 60 to 90 for bohemian and macramé, with sampling in front of both.
Open the referenceSpecification · Programme
Beadwork installs in an afternoon and takes months to arrive. The float belongs before production, not after delivery.
The published durations are: a quote within 48 hours of receiving specifications, sampling usually 16 to 20 days from an agreed brief with photos approved before the sample ships, and production for beaded décor 40 to 60 days after sample approval. Freight and the approval loops sit on top of those.
Where to put the float, and how many sample rounds the programme can afford. Those are the only two levers, because the production duration is published and fixed and installation takes an afternoon.

A bead package is unusual in that almost all of its time is spent before anything arrives on site, and all of the compressible time is in the decision-making rather than in the making.
| Stage | Published duration | Note |
|---|---|---|
| Enquiry response | Within 24 hours | Replies within one business day |
| Formal quote | Within 48 hours of receiving specifications | Presupposes a specification exists |
| Discovery call | Scheduled first on complex or multi-SKU projects | Adds to the front of the programme |
| Sampling | Usually 16 to 20 days from an agreed brief | Quoted separately from production |
| Sample photo approval | Before the sample ships | A client-side duration, not ours |
| Sample transit | Quoted per route | Depends on destination and service |
| Sample approval | Client-side | Production does not start until it is given |
| Production, beaded décor | 40 to 60 days after sample approval | The figure to plan against |
| Production, bohemian and macramé | 60 to 90 days after sample approval | A different category with a different duration |
| Testing, where required | Quoted per project | Arranged against the specified build |
| Freight and customs | Quoted per route | Landed duty paid quoting is available |
| Installation | One short visit | Nothing to compress |
None, because programme belongs in the programme. The relevant drawing content is anything that could trigger a re-sample, which means every tolerance, colour reference and hem profile should be resolved on the drawing before sampling starts.
A re-sample is 16 to 20 days plus transit plus another approval cycle, and it is the largest single programme risk on a bead package.
Work backwards from the installation date. Installation is one visit, late in the fit-out, after lighting commissioning. Before it, freight and customs. Before that, 40 to 60 days of production for beaded décor, starting at sample approval.
Before that, the client-side approval, the sample transit, and 16 to 20 days of sampling from an agreed brief. And before that, the brief itself, the quote — issued within 48 hours of receiving specifications — and whatever discovery the project needs.
The real dates: brief agreed, sample approved, production completed, shipped, installed. On a phased project the second phase is planned from those rather than from published figures, and the difference between the two is usually where the first phase lost time.
Less than the category does. Beaded décor runs 40 to 60 days after sample approval. Bohemian and macramé work runs 60 to 90, which is a materially different programme for a visually adjacent product.
Within beaded décor, a design needing a custom moulded bead carries die work ahead of production, and a design needing a test carries the laboratory turnaround. Neither of those durations is published, and both should be asked for against the specific build rather than estimated.
Float before production, not after delivery. The approval loops are where time can be recovered and they are also where it is usually lost, because a sample arrives, sits on a desk, and is approved three weeks later.
Naming an approval duration in the programme — and assigning it to a person — recovers more time than anything on the manufacturing side.
Through the fixing detail, which is earlier on the critical path than it looks. The header fixing has to be installed and load-tested before the panel arrives, so the fixing detail has to be issued well before shipment.
The second item is the lighting programme, because colour approval should follow lamp selection. On a tight job that creates a genuine conflict, and the resolution is to approve colour under a named reference light source and record the approval as conditional.
The programme carries durations. The specification carries anything that would cause a re-sample. The schedule carries quantities by colourway and destination, because those are what the production run is planned against.
Quantity by colourway matters to the programme as well as to the cost: a run split across several colourways is a different production plan from the same quantity in one.
By arriving late, almost always for the same reason: a specification that was not complete enough to quote from, so the quote waited, so the sample waited, so production started six weeks after everyone assumed it had.
The remedy is at the front. A complete ten-field specification can be quoted within 48 hours; an incomplete one generates a round of questions first.
Everything at once. The colourway, a full strand at full drop, the header detail and the hem. A sample round costs 16 to 20 days plus transit, so it should be asked to answer every open question rather than the most obvious one.
It adds an item to the order rather than to the programme. Spares and replacement strands are made in the same production run as the panels, with the same dye lot and the same counted sheet.
Ordering them afterwards means a second production cycle for a handful of strands, at the back of a queue, in a different dye lot. That is the single most common avoidable programme failure on a specified bead installation.
Production cannot be compressed by paying more. The 40 to 60 day figure is strung by hand against a counted sheet, panel by panel, and sampling is quoted separately and takes its own time.
What can be compressed is everything the project controls: the completeness of the brief, the speed of the approvals, and the decision not to re-sample for something that could have been drawn correctly the first time.
Good to know
Hold float before production starts rather than between delivery and installation. The compressible parts of this programme are the approval loops and the decision-making; production and freight are not compressible and installation is a single afternoon.
Everything that affects the programme: the colourway, a full strand, the header detail and the hem at full drop. A second sample round costs another 16 to 20 days plus transit, so the first sample should be asked to answer every open question at once.
It changes the end of the programme, not the middle. Spares and replacement strands are made in the same run as the panels, so they have to be ordered at the same time. Ordering them later means a second production cycle for a handful of strands.
The 40 to 60 day production figure starts at sample approval, not at order. A project that expects beadwork eight weeks from a first enquiry has not allowed for the quote, the brief, the sample, the transit and the approval, and those together are usually longer than the production.
The contractor, and it is on the critical path in a way people miss. The header fixing has to be installed and load-tested before the panel arrives, which means the fixing detail has to be issued well before the panel is shipped.
The actual dates: brief agreed, sample approved, production completed, shipped, installed. On a phased project the second phase will be planned from the first phase's real durations rather than from published ones.
Nothing from this page. Programme belongs in the programme. What does belong on the drawing is anything that would trigger a re-sample — a tolerance, a colour reference, a hem profile — because a re-sample is the single largest programme risk on a bead package.
Keep exploring
Reference
40 to 60 days after sample approval for beadwork, 60 to 90 for bohemian and macramé, with sampling in front of both.
Open the referenceSpecification
The dimensions, strand values, fixings and performance limits a drawing and schedule have to carry.
Open the referenceSpecification
Spare beads by colour, pre-made replacement strands, the cord spec, and who re-strings a strand on site.
Compare the optionsSpecification
After painting and lighting, before furniture — with the header loaded dry first and settling time allowed.
See the detailSpecification
The colour-count sheet, bead references, fixing details, the care card and the spares inventory.
See the detail
Start a conversation
Send a reference, a colour chip or a sketch. Minimums are set per design and confirmed per quote; sampling is quoted separately and usually runs 16 to 20 days from an agreed brief.