Installation sequencing

Beadwork goes in late, in one visit, and it needs the lighting commissioned first. Everything that goes wrong on site goes wrong because one of those three was not true.

The short answer

Beadwork installs after wet trades, painting, floor finishes and lighting commissioning, and before furniture and dressing. The header is fixed and load-tested before the panel is hung, the panel is lifted by its header rather than by the strands, and the strands need time to settle before the drop is judged.

Key takeaways

  • After painting, flooring and lighting commissioning. Before furniture and dressing.
  • Fix and load-test the header before the panel arrives on site.
  • Lift a panel by its header, never by the strands.
  • Allow settling time before judging the drop or the floor gap.
  • One visit, late. A panel installed early is a panel that gets dusty and damaged.

When should the panel arrive and go up?

When the panel arrives and when it goes up. Those are two different dates and treating them as one is the usual mistake: the panel can be delivered and stored, but it should be hung once, late, and then left alone.

The top of eight bead strands knotted over a turned wooden dowel, the first bead on each strand sitting tight against the knot.

The second decision is who protects it if trades return after installation.

Where does the sequence belong, drawing or programme?

Sequence from our own installation advice. Settling is judged on the hung panel.
StageRequirementWhy
Wet trades completeBefore beadwork arrives on sitePlaster and screed dust is the hardest thing to get out of a strand field
Floor finish completeBefore the drop is confirmedA floor build-up changes the floor gap
Painting completeBefore the header is fixedCutting in around a fixed header is slow and looks it
Lighting commissionedBefore the panel is acceptedColour reads differently under the final scheme
Header fixed and load-testedBefore the panel is hungA failed fixing with the panel on it damages the panel
Panel hungOne visit, by the headerLifting by the strands loads the knots in the wrong direction
Settling periodAllowed before the drop is judgedStrands settle under their own weight; judged on the panel
Furniture and dressingAfter the panel is hungAccess to the header is needed and furniture removes it
Protection or removalIf trades returnA hung panel in an active site collects everything

The sequence belongs in the programme and the preliminaries rather than on the drawing. What the drawing carries is the header fixing and the panel load, because the sequence depends on the fixing being installed and load-tested before the panel arrives.

Everything else on this page is a programme item, and it is more useful in a schedule of works than in a dimension block.

Which trades must finish before beadwork?

Place beadwork after wet trades, after the floor finish, after painting and after lighting commissioning. Place it before furniture and dressing, because access to the header is needed and furniture removes it.

Within that window, fix the header first, load-test it, then hang the panel by its header in one visit. Then allow the strands to settle before anybody measures the drop or signs off the floor gap.

Can a panel be installed in parts?

A panel cannot be part-installed. The strands are fixed to the header in a set order and the whole thing is a single object, so there is no version of it that goes up half way to meet a date.

The settling period is the other limit, and it is judged on the panel rather than scheduled. Strands settle under their own weight and the drop moves slightly; how long that takes depends on the bead material and the cord, so allow a day before the drop is measured or trimmed.

What does our installation advice keep repeating?

That handling is the recurring theme in our own installation advice: always lift a panel by its rod rather than by the strands, settle it after hanging, and store it in loosely tied bundles rather than loose.

Those three instructions exist because the failures they prevent — loaded knots, a panel judged before it has settled, a tangled panel out of a box — are the three that actually happen.

Which installation dates must be recorded?

The installation date, the fixing used, and the settling allowance taken before the drop was accepted. The third is the one that prevents a later argument about a drop that is twenty millimetres longer than the drawing.

Does bead material change the settling time?

It changes the settling. A heavy glass panel settles quickly and decisively, so the drop can be judged within the hour. A light acrylic, wood or bamboo panel settles more slowly and moves more, so the drop should be judged on a later visit.

It also changes the risk during installation. Glass beads chip when knocked against a frame; acrylic does not shatter. On a busy site that is a real argument for acrylic on anything at low level.

Does beadwork need programme or dimensional tolerance?

Programme tolerance rather than dimensional. Beadwork is a late item with a long upstream lead: sampling takes 16 to 20 days from an agreed brief, and production for beaded décor runs 40 to 60 days after sample approval.

That means the float belongs upstream, before production starts, rather than between delivery and installation. There is nothing to compress at the installation end: it is one short visit.

Why must the fixing precede delivery?

Through the fixing, before delivery. A panel delivered to a site with no fixing in place either waits in its carton, which is safe, or gets hung on something improvised, which is how panels come down.

The second coordination item is protection. If any trade returns after the panel is hung, somebody has to own either protecting it or taking it down, and that should be assigned rather than assumed.

Where do the handling instructions live?

The programme carries the sequence. The schedule of works carries the handling instructions, the load test requirement and the protection responsibility. The drawing carries the fixing and the load.

Handling instructions are worth repeating in the delivery documentation as well, because the person who unpacks the carton is often not the person who read the specification.

What goes wrong when sequencing slips?

Panels hung before the floor goes in, so the floor gap disappears under a tile build-up. Panels hung before lighting commissioning, so the colourway is accepted under site lighting and questioned under the final scheme.

And panels hung before the final trades, which collect plaster dust, paint overspray and handling damage in equal measure, then get cleaned badly before handover.

Why load-test the fixing before delivery?

The fixing, with a dead weight on it equal to the panel. That one test, done before the panel arrives, is the cheapest insurance on the package and is almost never carried out.

Who owns the first clean?

The first clean belongs to the installation rather than to maintenance. A panel hung on an active site needs dusting before handover, and that should be in somebody's scope.

Beyond that, a panel that will be taken down periodically for cleaning needs a fixing that releases, and that decision is made at specification stage rather than at the first clean.

Good to know

Questions buyers ask about Installation sequencing for beadwork

What does the as-built pack need?

The installation date, the fixing used, and a note of the settling allowance taken before the drop was accepted. The last one matters because a drop measured on the day of installation and a drop measured a week later are not quite the same number.

What has to appear on the drawing?

Not the sequence itself, which belongs in the programme and the preliminaries. What belongs on the drawing is the header fixing and the load, because the sequence depends on the fixing being installed and tested before the panel arrives.

What tolerance should be allowed?

Programme tolerance rather than dimensional. Beadwork is a late item with a long upstream lead time, so float belongs before it rather than after it. There is no useful tolerance on the installation itself: it is a single short visit.

What should be sampled before approval?

The fixing, loaded. Hanging a dead weight equal to the panel on the installed fixing before the panel arrives is the cheapest insurance on the whole package, and it is almost never done.

How does maintenance change the choice?

The first clean is part of the installation, not of maintenance. A panel hung on an active site will need dusting before handover, and that should be in somebody's scope rather than discovered at the client walk-round.

What is the performance limit here?

A panel cannot be installed in stages. The strands are fixed to the header in a set order and the panel is a single object, so it goes up in one visit or not at all. Part-installation to meet a programme date is not available.

Who coordinates the fixing?

The main contractor, against the specifier's drawing, and it has to happen before the panel is delivered. A panel delivered to a site with no fixing in place either waits in its carton, which is fine, or gets hung on something improvised, which is not.

Keep exploring

Related pages

Specification

Wall fixings

Plasterboard with and without a stud, timber, concrete and steel — and why the load has to be known first.